Solano Community College

Measure Q Project Updates

The Measure Q Bond was passed in November 2012.  The Citizens of Solano County invested 通过投票来改善和扩大索拉诺社区的设施 学院区与Q债券措施的通过.  The projects listed below are the currently active projects and their status.

July 2023

Fairfield Campus Active Project Updates

Solar Energy

Solar Energy Site Map (Parking Lots 2 & 4)

 

 

Solar Energy - Fairfield Campus

说明:该项目包括安装额外的光伏阵列 (PV’s),电池储能系统(BESS),以及更多的电动汽车(EV)充电 stations.  项目目标是抵消费尔菲尔德校区目前的能源消耗. 

Budget:  $14,000,000

Current Status:  该项目通过设计-建造-运营-维护的交付方式完成

  • Bid Phase – Complete
  • Design Phase – PV and EV design approved by DSA (Division of State Architect); BESS design DSA review in process with DSA.
  • Construction Phase – Module installation complete; underground utility work ongoing; electrical work ongoing.

 Completion Target: December 2023

On Campus Housing

On Campus Housing Renderings

 

On-Campus Housing - Fairfield Campus

本项目从需求评估和可行性分析开始; which have been completed. 根据这些结果,开发设施 program for an expected multi-phased housing community.  Completing a State (SB169) funding grant application for submittal in July 2023.  This grant, if awarded, will 将用于兴建第一期房屋社区-低于市价的房屋 全日制学生获得特定的经济援助. Concurrently, exploring 其他住房类型可能的公私合作伙伴方案 在社区内,这可能包括为有家人/配偶/家庭的学生提供住房 dependents, faculty and staff, and active seniors.

Budget:  $850,000

Current Status:

  • 设计前阶段-完成第一阶段的设施计划及发展第三阶段的招标

Completion Targets:

  • SB169 Grant Application submission July 2023
  • 预期的P3合作伙伴征集和选择:2023年7月- 2024年1月

B300 Renovation

 

 

 

 

 

Building 300 Renovation - Fairfield Campus

项目描述:该项目将对现有的300号楼进行翻新,重点是室内装修 刷新,屋顶更换,温度控制和用户舒适度.  The project 目标是使老化的建筑现代化,以满足当前的标准. 

Budget:  $2,000,000

Current Status:

  • Design Phase – Complete
  • Bid Phase – Project bid was canceled; bid package will be revised and re-issued over the summer
  • 施工阶段-预计施工2023年12月至2024年7月

Completion Target: July 2024

Early Learning Center Expansion

New Modular Building Fabrication

 

 

Early Learning Center Expansion - Fairfield Campus

描述:该项目是早期学习中心的一个扩展,服务于大约 forty (40) children. 这就需要在早教中心增建一座新楼 Center location. 该项目还将包括外部游乐区的升级 as determined by regulations/code. 

Budget:  $5,000,000

Status:

  • Design Phase – Complete
  • Bid Phase – Complete
  • 施工阶段-建筑制造完成,建筑部分交付 to site; sitework was delayed due to wet weather and is now back on track to completion

Completion Target: August 2023

FF Substation 3 and 4

Substations #3 and #4 Locations

 

更换3号和4号变电站(基础设施改善)-费尔菲尔德校区

描述:本项目是对现有老化变电站进行更换和/或现代化改造 #3 and Substation #4.

Budget:  $9,250,000

Current Status:

该项目通过设计-构建交付方法完成.

  • Criteria Documents Phase – Complete
  • Bid Phase – Complete
  • Design Phase – Project design is ongoing; Design-Build team working with DSA (Division of State Architect) to expedite contract document development; DBE (Design-Build Entity) is anticipating drawing approval in mid-July
  • Construction Phase – Anticipated construction August 2023 – September 2024; site clearing and grubbing on going

Completion Target: September 2024

FF Swimming Pool Deck Replacement

Existing Pool Deck

 

 

游泳池甲板更换(基础设施改善)-费尔菲尔德校区

项目描述:本项目包括拆除和更换现有的游泳池 游泳池周围的甲板和瓷砖,安装室外淋浴器和新的大门, and ADA upgrades. 

Budget:  $1,293,900 ($700,000 Measure Q; $593,900 State Schedule Maintenance)

Current Status:

  • Design Phase – Complete
  • Bid Phase – Complete
  • Construction Phase – Anticipated construction June 2023 – November 2023; demolition of deck ongoing

Completion Target: November 2023

FF Campus Central Plant

Existing Central Plant

 

 

中心厂房更换(基础设施改善)-费尔菲尔德校区

描述:该项目将使费尔菲尔德校区的中央工厂和工厂现代化 提供供热系统的部分电气化.

Budget:  $12,500,000

Current Status:

  • Design Phase – Complete
  • Bid Phase – Complete; contract execution in progress
  • 施工阶段-预计施工2023年5月- 2024年8月

Completion Target: August 2024

Quad Water Conservation

Quad Water Conservation Rendering

Quad Water Conservation - Fairfield Campus

项目描述:该项目包括对南侧四边形区域的设计更新 new Library Learning Resource Center. The revised quad design will implement strategies 这将优先考虑节水、可持续性和最小化/减少操作 and maintenance.  

Budget:  $950,000

Current Status:

  • Pre-Design Phase – Complete
  • Design Phase – June 2023 – August 2023
  • Bid Phase – Anticipated December 2023
  • 施工阶段-预计2024年2月- 2024年8月

Completion Target: August 2024

FF Parking Lot Improvments

Fairfield Campus Map Showing Locations of Work

 

Parking Lot Repairs/Improvements

Description:  该项目将解决校园内日益恶化的停车场和通道问题.  工作范围包括密封第3地段,重铺F地段,替换第1段 校园内道路(沿校园前方的路段). 

Budget: 

Current Status:

  • Design Phase – Complete
  • 投标阶段-已确定最低投标人,并计划向董事会推荐 July
  • 施工阶段-预计2023年7月至10月施工

Completion Target:  October 2023

 

Vacaville Center Active Project Updates

VV Annex HVAC Roof Replacement

HVAC/Roof

Vacaville中心附属建筑-护理法案升级(暖通空调/屋顶更换)项目 - Vacaville

项目描述:本项目通过更换暖通空调设备,对室内通风进行升级改造 controls. The existing roof will also be removed and replaced.  

Budget:  $3,811,037 ($2,700,000 Measure Q; $1,111,037 CARES Act)

Current Status:

  • Design Phase - Complete
  • Bid Phase – Complete
  • 施工阶段-通过提交流程和采购长期领先的设备; on site construction to begin August 2023; contractor has completed pre-construction HVAC system testing

Completion Target: February 2024

Vallejo Center Active Project Updates

Vallejo Autotech Security 

 Masonry Perimeter Wall Foundation

 

Vallejo Auto Tech Vehicle Security Project - Vallejo

描述:本项目将增强汽车周边的屏障 车辆堆场增加安全性,更好地保护正在使用的车辆 for class instruction.

Budget:  $850,000

Current Status: 

  • Design Phase – Complete
  • Bid Phase – Complete
  • Construction Phase – Working on gates and irrigation

Completion Target: July 2023